...

Evaluation of plant status by the fuel range water level indicators of

by user

on
Category: Documents
75

views

Report

Comments

Transcript

Evaluation of plant status by the fuel range water level indicators of
Attachment 1-2
Evaluation of plant status by the fuel range water level indicators of Unit-1
1. Principle of the fuel range water level indicators
A typical fuel range water level indicator used in BWR plants is illustrated in Figure 1. It
measures the reactor water level by measuring pressure difference (Hs – Hr) of two
instrumentation piping systems (reference condensing water chamber side piping, hereafter
described as reference leg, and reactor side piping) while keeping the water head Hs in the
reference water head at a certain fixed value.
If the water level in the reference leg decreases due to evaporation, etc., the Hs, which
should be constant, is reduced. But, what is measured (or rather observed) is only the
pressure difference, it cannot be distinguished whether Hs has decreased or Hr has
increased. As a consequence, the apparent reactor water level seems to have increased
(Figure 2). Figure 3 illustrates vertical positioning of the fuel range water level indicator in the
drywell (D/W). When only the water level in the instrumentation piping on the reference leg
decreases, the reactor water level may be indicated as having increased by L1 (about 7m) in
the figure at the maximum. On the contrary, when only the water level in the instrumentation
piping on the reactor side decreases, the reactor water level may be indicated as having
decreased by L2 (about 3.3m) in the figure at the maximum. It should be noted that the water
levels in the piping outside the D/W will be maintained with little changes, because the
ambient temperatures are kept low.
2. Assumptions made in the analysis
The following contradictions have been noticed in the analysis results made public so far
(MAAP results on May 23th, 2011).

Once the reactor water level dropped to the bottom of active fuel (BAF), the water
head in the fuel region was considered not to have been formed. But the fuel range
water level indicator (Channel-A) showed the level was at the top of active fuel (TAF)
+0.45m at 21:30 on March 11th.

No water was injected thereafter, nevertheless the water level increase was indicated
(Figure 4).
These suggest that, when the fuel range reactor water level indicator (Channel-A) was
restored at 21:30, the water head in the reference leg had already been decreased (Figure
5-1).
One possibility for the water level decrease in the reference leg can be gaseous leakage
Attachment 1-2-1
from the reactor vessel. If it occurs, steam leaks into the D/W, the D/W atmosphere
temperature increases and the water in the piping is heated up. In addition, when the reactor
pressure decreases, the saturation temperature of water in the instrumentation piping
decreases and thus evaporation is facilitated.
Possible paths of gaseous leakage from the reactor vessel to the D/W are the in-core
instrumentation dry tube (Figure 6) or the main steam line flange gasket. The in-core
instrumentation dry tube can be damaged when fuel temperatures are elevated. The main
steam line flange gasket may lose its airtightness at temperature of about 450 deg C. In the
new MAAP analysis, therefore, two gaseous leakages (0.00014m2 and 0.00136m2) have
been assumed at the timings when the core damage started and when the reactor gas
temperature reached 450 deg C.
(Note) Causes of change of water levels indicated on the fuel range water level indicators
The fuel range water level indicator (Channel-A) indicated TAF +0.45m at 21:30 on March
11th; this slightly increased thereafter until 22:20 and reached TAF+0.59m, where it
remained until 23:24. It increased again to TAF+1.3m at 00:30 on March 12th and stayed
there until about 06:30. The Channel-B indicator, on the other hand, indicated TAF+0.53m at
01:55 on March 12th and stayed there. The fuel range reactor water level indicators
(Channel-A and Channel-B) started to decrease at 06:30 on March 12th and thereafter. And
after about 12:30 on that day they remained roughly constant. The following items are
relevant examinations into the status of the reactor water levels and the fuel range water
level indicator piping.
(1)
Water levels indicated from 21:30 on March 11th to 00:30 on March 12th
As discussed above, when the fuel range water level indicator (Channel-A) showed
TAF+0.45m at 21:30 on March 11th, the actual reactor water level is considered to have
been below BAF and therefore the water level in the reference leg is considered to have
decreased at that timing (Figure 5-1). The reactor water level increase seen on the chart
over this time period would be considered to have been caused by gradually decreasing
water in the reference leg by evaporation, since no water was being injected during this
time period.
In the MAAP results, fuel melting had already occurred during this time period and the
reactor gas temperatures were elevated. Therefore, gaseous leakage from the reactor
vessel seems likely to have occurred. If gases leaked and the D/W temperature increased,
the water temperature in the reference leg could exceed its saturation temperature and
the water level therein could evaporate, thus indicating higher values on the indicator.
Attachment 1-2-2
The reason has not been identified why the fuel range water level indicator (Channel-A)
increased again after 22:20, until then it had remained at a constant value for a while. The
water level and saturation temperature of the water in the reference leg could have been
changeable due to the changes of the pressure containment vessel (PCV) temperature
and reactor pressure, if gaseous leakage had occurred from the reactor vessel.
(2)
Water levels indicated from 00:30 to about 06:30 on March 12th
There is a possibility that the water level changes could not have been detected and the
indicator value could have stayed at an elevated value. The reasons therefore could be:
the water level in the reference leg decreased to the level of PCV penetration, while the
reactor water level dropped below BAF and reached the level of the tap position of the
reactor side piping (TAF– about 5.5m) (Figure 5-2).
According to the new MAAP results, the reactor vessel ruptured at about 01:50 on
March 12th. But the accident progression scenario may depend on the analytical model,
because there is a limitation in simulating complicated phenomena like fuel relocations of
molten fuel after core damage. Therefore, the analysis results may not mean that the
reactor vessel was ruptured during this time period.
It should be noted that the Channel-B fuel range water level indicator showed a lower
value than that of Channel-A by about 0.80m. One possible reason for this is the water
level decrease in the Channel-B reference leg was less than that of the Channel-A piping
due to the larger water inventory in the former piping because its piping routing in the D/W
was longer than that of Channel-A by about 3m in the horizontal direction.
(3)
Water levels indicated after 06:30 on March 12th
It can be considered that the PCV temperature increased, for instance, because the
molten fuel fell on the pedestal due to reactor vessel rupture, the water in the reactor side
piping started to evaporate and was evaporated before the D/W penetration (Figure 5-3).
If this is true, the pressure difference is increased between the reference leg and reactor
side piping, and the water level indicators show decreasing values regardless of the
actual reactor water level.
Once the water level changes in the instrumentation piping terminated at about 12:30
on March 12th, constant values might have been indicated thereafter on the water level
indicators.
Attachment 1-2-3
Reference condensing
water chamber
基準面器
Differential
pressure
transmitter
Hs
Hr
LT
差圧計
Reference chamber 基準面器
side piping
(Reference leg)
側配管
Reactor side 炉側配管
piping
(Variable leg)
Figure 1 Fuel range water level indicator
Reference condensing
water chamber
基準面器
Reference condensing
water chamber
基準面器
炉内水位
Actual
の実際の
water
状況
level
in the
reactor
差圧計
LT
Differential
pressure
transmitter
Apparent
基準面器
water
level
から水位
increases
が減少す
due to
ることで、
decreased
見かけ上
water level
の水位が
in上昇
the ref.
leg
差圧計
LT
Value indicated on the
water
level indicator
水位計の指示値
実際の水位
Actual
water level
in the reactor
基準面器
Reference
leg
側配管
炉側配管
Variable
leg
Figure 2 Water level indicated when the water level decreased in the instrumentation piping
Attachment 1-2-4
PCV
Reference condensing
凝縮槽
water chamber
Reference
water level
基準面
Reference
leg
基準面器側配管
L1=7036.8 (mm)
L2=3332 (mm)
Variable leg
炉側配管
LT
Differential pressure
差圧計
transmitter
Figure 3 Vertical positioning of fuel range water level indicator in the D/W
Attachment 1-2-5
6
Downcomer
ダウンカマ水位
water level
シュラウド内水位
Water
level inside shroud
5
Measured
(Fuel range (A))
実測値(原子炉水位(燃料域)(A))
Measured
(Fuel range (B))
実測値(原子炉水位(燃料域)(B))
4
3
2
1
TAF
Reactor
water level (m)
原子炉水位(m)
0
-1
-2
-3
BAF
-4
-5
-6
-7
-8
-9
-10
3/11
12:00
3/11
18:00
3/12
0:00
3/12
6:00
3/12
12:00
3/12
18:00
Date
日時/ Time
Figure 4 Water level changes on the fuel range reactor water level indicators
Attachment 1-2-6
3/13
0:00
PCV
Reference condensing
凝縮槽
water
chamber
基準面 water level
Reference
Reference
water head
蒸発による基準
decrease due
水面低下
to evaporation
基準面器側配管
Reference leg
Variable leg
炉側配管
Differential pressure
差圧計
transmitter
LT
Figure 5-1 Water level changes of the reactor and fuel range water level indicators
(from 21:30 on March 11th to about 00:30 on March 12th)
PCV
Reference凝縮槽
condensing
water chamber
Reactor side piping tap
炉側配管タップ
Differential pressure
差圧計
transmitter
LT
Figure 5-2 Water level changes of the reactor and fuel range water level indicators
(from about 00:30 to about 06:30 on March 12th)
Attachment 1-2-7
PCV
Reference condensing
凝縮槽
water chamber
Reference leg
Water 蒸発による
level decrease
水面低下
due to
evaporation
Water level
decrease
蒸発による
水面低下
due to evaporation
Reactor
side piping tap
炉側配管タップ
Variable leg
Differential差圧計
pressure
transmitter
LT
Figure 5-3 Water level changes of the reactor and fuel range water level indicators
(after about 06:30 on March 12th)
Attachment 1-2-8
Legend
SRM Source range monitor
IRM Intermediate range monitor
TIP Travelling in-core probe
SRM
/ IRM
SRM/IRM
Dry
tube
ドライチューブ
TIP
TIPドライチューブ
Dry tube
Inside
PCV
PCV内
(Inside
(D/WD/W)
内)
PCV外
PCV
Housing
for neutron
中性子束計装
instrumentation
ハウジング
SRM
/ IRM
SRM/IRM
Driving mechanism
駆動装置
継ぎ手部
Joint
索引装置
Indexer
Figure 6 Leak path through the in-core instrumentation system
Attachment 1-2-9
Fly UP